Extending our presence in Pirapora II, Brazil

While running 76MWp at Pirapora Phase II we ve been asked by our customer to deliver – electrical and mechanical works – another 10MWp at the same project by 10th of April 2018.  We have enforced our manpower by handling 200 Brazilians and 30 expats and we intend to be punctual on the work time schedule and proceed with commissioning at that day.